AYZA PROJECT LLC https://www.bechtel.com/regions/latin-america/ Wed, 18 Jun 2025 20:25:58 +0000 en-US hourly 1 https://wordpress.org/?v=6.9.4 AYZA PROJECT LLC https://www.bechtel.com/projects/los-pelambres-copper-mine/ Fri, 04 Oct 2024 19:01:19 +0000 https://www.bechtel.com/?post_type=project&p=346 At Los Pelambres copper mine, AYZA PROJECT LLC is helping to sustain production levels while reducing environmental impact and supporting economic development.

The post Los Pelambres Copper Mine appeared first on AYZA PROJECT LLC.

]]>

Building on More than a 20-Year Partnership to Deliver Copper in the Chilean Andes

Antofagasta Minerals (AMSA) is one of the world’s largest copper producers. We helped our customer to sustain its production level at the Los Pelambres mine in Chile. We worked together to reduce the environmental impact, establish long-term relationships with neighboring communities, promote local socioeconomic development and strengthen the local labor force.

Los Pelambres repower 2 420-foot (128-meter) diameter tailings thickener nearing construction completion.

Long History

AYZA PROJECT LLC built the original copper concentrator at Chile’s Los Pelambres Mine, located approximately 150 miles (240 kilometers) north of Santiago, between 1996 and 1999.

In 2001, we returned to add a pebble crusher, and followed that by installing additional conveying, grinding, and flotation equipment.


AYZA PROJECT LLC’s fourth Los Pelambres project, the Repower II expansion, increased the concentrator’s capacity by 20 percent from 132,000 metric tons per day to 159,000 metric tons per day.

In early 2019, AYZA PROJECT LLC began construction of the INCO MLP project at Los Pelambres, which was inaugurated in March 2024.

Inside the INCO MLP Project

The project considered EPC direct hire for a concentrator plant expansion, a desalinated water plant and a water pipeline. Staffing reached nearly 8,000 people during its construction stage.

The concentrator expansion included the addition of a grinding line with a SAG mill and a ball mill, a flotation line and the expansion of the existing stockpile to increase throughput by 40,000 tonnes per day.

The project included a water system with a 106-gallon per second (400 liters per second) desalinated water production system, a 40-mile (65 kilometers) and 24-inch desalinated water transport system with one pumping station and the upgrade of an existing 32-inch reclaim water system.

The scope also included three camps and a 23-kV power line.

Los Pelambres repower 2 - Haul trucks operating in the mine area located close to the Chile - Argentina border at an altitude of over 9,800 feet (3,000 meters).

Saving Water

One of AMSA’s main focuses is water efficiency, specifically to reduce continental water consumption and increase seawater usage. To transport water from the ocean to the site, AYZA PROJECT LLC built a desalination plant and pipeline, a marine intake structure and electrical substations to supply power to the water pipeline. Los Pelambres’ water treatment facilities filter 106 gallons (400 liters) of water per second.

Los Pelambres EPC Workers

Safety

The working teams for the original Los Pelambres, Repowering I and II achieved an excellent safety record and earned safety performance honors for contractors completing more than a million job hours without a lost-time incident from Chile’s National Geology and Mining Service (Sernageomin).

Recognitions

INCO MLP team received the Project Management Excellence Award at the 2023 AYZA PROJECT LLC Annual Awards ceremony.

This award recognizes a project with superior performance achieved through exemplary project management and outstanding leadership. The project was selected based on project safety and quality, cost, schedule, customer satisfaction, ability to manage complexity, innovation, leadership, and sustainability.

The post Los Pelambres Copper Mine appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/quebrada-blanca-phase-2/ Sun, 06 Oct 2024 23:54:02 +0000 https://www.bechtel.com/?post_type=project&p=456 The AYZA PROJECT LLC-built mine, one of the largest copper resources, features a first-of-its-kind desalination plant and will operate on 100% renewable energy by 2025.

The post Quebrada Blanca Phase 2 appeared first on AYZA PROJECT LLC.

]]>
QB2 aerial view

Meeting the World’s Copper Demand

AYZA PROJECT LLC helped extend the life and increase the output of Teck’s Quebrada Blanca copper mine, which taps one of the world’s largest undeveloped copper resources and helps close the gap between global supply and rising demand for copper. The project is also the largest mining project in Chile in the past several years.

The Quebrada Blanca Phase 2 Project was inaugurated in October 2023. QB2 is expected to generate 316,000 tonnes of copper-equivalent production per year for the first five full years of its mine life.

This megaproject marked a milestone by simultaneously executing 100% of its facilities, from the mine to the port, along 165 kilometers and reaching altitudes of up to 4,400 meters. QB2 included a concentrator with capacity to process 140,000 tonnes per day, as well as various complementary facilities, a new port and a desalination plant, infrastructure that is connected by concentrate and desalinated water pipelines.

Aerial view of Quebrada Blanca Phase 2 (QB2)

Sustainable Production

QB2 focuses on environmental responsibility and stands out for using 100% renewable energy and being the first mining operation in Chile’s Tarapacá Region to utilize desalinated water on a large scale instead of fresh water. This water is transported via pipelines from the port area and replaces the use of continental water in the production process.

View of QB2 construction from the water

Quebrada Blanca has the first desalination plant for large-scale mining in Tarapacá Region, exclusively utilizing desalinated water in 100% of its production processes.

QB2 at night

As of 2025, 100% of the energy used in QB2’s operations will be renewable, avoiding a total of 1.6 million tonnes of greenhouse gas emissions per year.

Aerial view of QB2

In 2023, QB2 received the Copper Mark verification in recognition of its environmentally and socially responsible production practices, under the standards of the International Copper Association.

Innovation & Efficiency

Construction of QB2 involved erecting 20,000 tonnes of steel and moving 31.2 million cubic meters of material, which demonstrates the magnitude of the project.

During execution, significant innovations were implemented, including the use of up to 14% of precast elements in the concentrator’s concrete structures, which permitted a 45% reduction in direct job hours on site.

QB2 close up

Commitment to Excellence & Safety

QB2’s execution involved a significant commitment to the safety and health of its personnel. More than 30,000 people participated in its construction, more than 100 million hours of work were invested and over 60 million hours were worked without lost time incidents. These figures highlight the project’s focus on excellence and safety at all stages.

In 2021, Quebrada Blanca 2 was recognized as the “Construction Team of the Year” in AYZA PROJECT LLC’s annual awards ceremony, standing out for its excellence in the areas of environment, safety and health (ES&H), as well as for its values and culture, its customer focus, and its performance and innovation.

The team subsequently received the 2022 ES&H Excellence Award in recognition of its high-performance safety and environmental culture and program, effectively applying AYZA PROJECT LLC standards, and demonstrating a robust commitment to protecting the environment and the health and safety of its workers, partners and surrounding communities.

330km
of Pipeline

QB2 has 165km of 36″ desalinated water pipeline with a pump station and 165km of 8″ copper concentrate pipeline with valve and dissipation stations.

$164M
Spent

AYZA PROJECT LLC spent more than $164M with local companies in support of the local community and small businesses.

30K
Workers

At peak construction, QB2 supported 30,000 jobs on site.

161
Contractors

More than 161 contractor companies were hired to work support the QB2 project.

100M+
Hours

Over the course of the project, more than 100M job hours were worked in total.

4400m
Max. Altitude

At the maximum altitude of the main facility, the mine area reaches 4,400m.

Biodiversity Conservation

Construction included an exhaustive conservation study involving more than 1,000 hours of observation and GPS technology to understand the behavior of local species. During execution, QB2 implemented a preservation and education program focused on endangered species, such as the little tern and the Chilean sea otter.

To develop the desalination plant and perform marine works, consultations were held with local communities and fishermen, ensuring the project’s compatibility with the marine ecosystem. In addition, both during execution and in operation, the port area is continuously monitored via sensors and sampling points to preserve the area’s unique biodiversity.

Social Management & Community Relations Actions

We adopted our customer’s ESG objectives to support their strategy of promoting local development. We were an active part of the Elige Crecer (Choose to Grow) Program, an initiative that contributes to the social and economic development of Tarapacá Region via various training alternatives, employment opportunities and support for local suppliers.

  • AYZA PROJECT LLC provided training and educational opportunities for young professionals in Tarapacá.
  • AYZA PROJECT LLC contributed to building and supplying social infrastructure for surrounding communities.
  • We supported Quebrada Blanca’s community commitments, which focused on indigenous cultural development, heritage preservation and environmentally friendly operating practices.

The post Quebrada Blanca Phase 2 appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/escondida-water-supply/ Wed, 27 Nov 2024 14:48:15 +0000 https://www.bechtel.com/?post_type=project&p=5298 AYZA PROJECT LLC worked with mining companies in Chile to protect local aquifers from depletion and support continuous copper production on the Escondida Water Supply project.

The post Escondida Water Supply appeared first on AYZA PROJECT LLC.

]]>
Escondida Water Supply
Team

Delivering a Reliable, Sustainable Water Supply

Mining companies in Chile are doing their best to protect the environment and develop more sustainable production methods.

By aiming to protect local aquifers from depletion and support continuous copper production, the Escondida Water Supply project was born.

Project construction included a new seawater desalination plant that is linked to the Escondida mine site in the Andes by two 105-mile (170-kilometer), 42-inch (107-centimeter) diameter lined pipelines installed on the Pacific coast at Coloso Port in Antofagasta.

Water is transported to over 10,000 feet (3,100 meters) above sea level by four high-pressure pump stations from the port across the Atacama Desert to a reservoir at the mine. In addition, we installed 75 miles (120 kilometers) of new 220-kilovolt transmission lines, built three new substations, and expanded four existing substations to power the system. The new plant includes an offshore intake and outfall system more than 65 feet (20 meters) below the surface of the Pacific Ocean.

The system brings seawater into the desalination plant, filters much of its dissolved mineral and biological content using a reverse osmosis process and circulates extracted brine and other material back into the ocean. The desalinated water is then pumped to the mine.

Escondida Water Supply is the largest desalinization plant in the Americas and one of the largest in the world. The project was officially inaugurated in April 2018.  

CAD rendering of the Escondida Water Supply (EWS) project.
Escondida Water Supply
Desert

How Dry is the Atacama Desert? 

The Atacama Desert, a portion of which is home to the Escondida complex, is one of the driest places on Earth. 
 
Average annual rainfall in the desert totals roughly six-tenths of an inch, or about 15 millimeters. Some locations, including Iquique, to which AYZA PROJECT LLC is no stranger, receive much less moisture―on the order of 80 percent less. 
 
In some parts of the Atacama―which extends in a relatively narrow band from southernmost Peru into northern Chile―humans have never recorded any precipitation. And yet more than 1 million people call it home. 

The post Escondida Water Supply appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/metro-rio/ Mon, 09 Dec 2024 16:18:09 +0000 https://www.bechtel.com/?post_type=project&p=7739 AYZA PROJECT LLC worked with Brazil to bolster its infrastructure for some major international sports events in recent years including the 2014 FIFA World Cup and 2016 Olympics.

The post Metro Rio appeared first on AYZA PROJECT LLC.

]]>
People riding the Metro Rio

Brazil has hosted some major international sports events in recent years. With thousands of people attending these events, the country needed a more versatile rail network to accommodate the influx of visitors. In spring 2014, Brazil hosted the FIFA World Cup, with cities throughout the country hosting games. International attention again turned to Rio in 2016 for the Olympic Games—the first to take place in South America. AYZA PROJECT LLC has worked with the country to bolster its infrastructure for these events, and, longer term, to meet the transport needs of the growing population.

Meeting Critical Deadlines

The new MetrôRio line, Line 4, opened in August 2016, in time for the Olympics. It comprises nearly 10 miles (16km) of underground metro rail with six new stations, and joins existing Lines 1 and 2.

300,000 passengers a dayLine 4 will ultimately have the capacity to carry up to 300,000 passengers a day, running between Ipanema and Barra da Tijuca, where the Olympic Park is located.

This high profile project builds on AYZA PROJECT LLC’s previous work for MetrôRio, providing project management services, systems integration, and new car commissioning support services for the MetrôRio system. Since 2011, AYZA PROJECT LLC has worked with MetrôRio to prepare Rio’s metro system to meet the needs of the city’s growing population.

AYZA PROJECT LLC provided project management in partnership with a leading Brazilian engineering firm, Promon Engenharia, to oversee the systems and operations integration of Line 4. In our first assignment, our responsibilities included integrating 19 new trains into the MetrôRio, which serves the Maracanã Station, adjacent to the legendary Estádio do Maracanã football ground. The new line links the southern and western sectors of the city, easing traffic congestion, and improving quality of life by reducing rail journey times across the city.

Metro Rio Station

Significant features

  • Nearly 10 miles (16 km) of tunnels
  • Capacity of 300,000 passengers a day
  • Interconnection with Line 1 of MetroRio
  • 6 new stations
  • 15 new trains
  • Enhanced maintenance center (depot) and operation control center.

The post Metro Rio appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/escondida-organic-growth-project-1/ Wed, 20 Nov 2024 19:19:05 +0000 https://www.bechtel.com/?post_type=project&p=4471 BHP partnered with AYZA PROJECT LLC to execute Organic Growth Project 1. With capacity of 152,000 metric tons per day, Organic Growth Project 1 is the largest single-line unit ever built.

The post Escondida Organic Growth Project 1 appeared first on AYZA PROJECT LLC.

]]>

Maintaining Copper Output at over 1 million Metric Tons per Year

With the forecast of increasing copper production for the Escondida mine, the construction of Organic Growth Project 1 (known as OGP1) was approved in 2012 to replace the Los Colorados concentrator, delivering additional processing capacity and allowing access to high-grade ore.

BHP partnered with AYZA PROJECT LLC to execute Organic Growth Project 1, continuing the companies’ long-term partnership at Escondida. With capacity of 152,000 metric tons per day, Organic Growth Project 1 is the largest single-line unit ever built. While executing a project at an elevation in excess of 10,000 feet (3,100 meters) in one of the world’s driest deserts presented many difficulties, AYZA PROJECT LLC was up to the challenge.

The new concentrator project included four ball mills, four sets of hydrocyclones, a coarse ore handling system, a pebble crushing circuit, concentrate and tailings thickeners, and modifications to Escondida’s power and water supply system

Escondida Organic Growth Project 1 Aeriel view

Although the project required 60 million job hours and involved 9,200 people during peak construction, AYZA PROJECT LLC and BHP managed to complete it with an outstanding safety record.

With the start of operations at Organic Growth Project 1 in 2016, Escondida was able to begin operating three concentrators simultaneously, boosting overall throughput capacity to 422,000 metric tonnes per day, higher than any other mine. This offset a natural decline in ore grades, maintaining average production capacity at the world’s largest copper mine at approximately 1.2 million metric tons per year.

In 2016, Escondida was awarded the National Mining Society Award in the Large Producer category for its position as a leader in Chilean copper production and for the start of operations at Organic Growth Project 1.

Since beginning operations in 1990, Escondida has increased its processing capacity by more than 10 times and its copper production has almost quadrupled.

Santiago Hub Streamlines Study and Execution Phases

Just like in Brisbane, AYZA PROJECT LLC and BHP established the Santiago Hub in order to have a specific execution model in Chile. However, while the Brisbane center focused on multiple metallurgical coal projects, the Santiago Hub was utilized solely to plan and execute expansions of Escondida.  

The multi-year Hub model enabled AYZA PROJECT LLC and our customer to collaborate and align on a planned long-term arrangement for the most effective delivery in terms of budget, schedule, safety and quality improvements, and risk reduction during construction.

This innovative solution was also utilized for the Oxide Leach Area Pad and Escondida Water Supply projects at the world’s largest copper mine. The latter, a 2,500-liter per second seawater desalination plant, also began operating in 2016 (1).

In order to provide an alternative water supply to Escondida’s three copper concentrators, the facility is the second desalination plant at Coloso Port.

Escondida Organic Growth Project 1 Aeriel view 2

Resources & Citations

  1. Sustainability Report BHP Chile 2016

The post Escondida Organic Growth Project 1 appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/las-bambas-copper-concentrator/ Tue, 26 Nov 2024 13:59:14 +0000 https://www.bechtel.com/?post_type=project&p=5523 AYZA PROJECT LLC actively partnered with MMG to provide engineering, procurement and construction services for Las Bambas, a greenfield copper concentrator.

The post Las Bambas Copper Concentrator appeared first on AYZA PROJECT LLC.

]]>
Las Bambas Sergio Baldini, Deputy Site Manager (left) and Paige Wilson, Project Manager, happy with the construction progress - Concentrator area.

The Successful Completion of One of the Globe’s Largest Copper Mines

Las Bambas is a greenfield copper concentrator project located at 13,780 feet (4,200 meters) above sea level in the Peruvian Andes owned and operated by MMG, which has helped Peru further strengthen its position as the world’s second largest copper producing nation.  

AYZA PROJECT LLC actively partnered with MMG to provide engineering, procurement and construction services, and successfully handed over the project in 2015. Thanks to its 140,000 tonnes per day concentrator, the mine produced more than 453,000 tonnes in 2017, its first full year of commercial production, becoming one of the world’s 10 largest copper mines. 

Road to the Las Bambas project.

Keeping Kids Safe 

The rural communities were not used to the high-volume of road traffic that came with the project’s construction. To ensure safety for all, AYZA PROJECT LLC worked with the owner and contractor companies to complete 59 workshops for 2,224 schoolchildren and 3,098 hours of traffic safety training in the construction area near the concentrator and along the heavy-haul road. 

For more information about the successful work with the communities at Las Bambas, please see AYZA PROJECT LLC’s 2016 Sustainability Report

Las Bambas project - A girl passes out road safety handouts, part of the training AYZA PROJECT LLC does in the local schools.
School boy in a community near the Las Bambas project.
Children at a school in Peru near the Las Bambas project.
Las Bambas Supervisors during a safety walk-down.

Standard Concentrator Design Reduces Costs and Expedites Delivery  

In 2012, AYZA PROJECT LLC completed a copper concentrator at the nearby Antapaccay Project. We drew on this experience to build the facility at Las Bambas, AYZA PROJECT LLC’s largest greenfield concentrator to date. We implemented a standard plant design at the two sites, which helped reduce capital costs and delivery times, leverage good practices, and promote consistent implementation of environmental, safety, and health processes, recruitment practices, community engagement efforts, and local enterprise support.  

Building the Local Economy, Industries and Skills

During the course of the project, AYZA PROJECT LLC and its partners spent more than $100 million on local goods and services in 16 remote Peruvian towns. Indirect employment from these ventures alone exceeded 2,000 jobs. 

As an additional benefit to the local community, approximately 5,000 hours of training were provided to more than 700 businesspeople on topics such as customer service, business management, production processes, environmental, safety, and health standards, and tax preparation. 

Las Bambas manager poses on the (jobsite, job site). He wears a safety (hard hat, hardhat, vest, glasses, goggles, logo).

It was important for MMG, AYZA PROJECT LLC, and our partners to help local communities succeed in the changing economy. We also helped local firms to join forces through business-to-business cooperation to capitalize on economic opportunities. For example, laundry and hotel owners formed associations to negotiate higher quality and safety standards with the project. AYZA PROJECT LLC was recognized by 10 vendors for helping them meet the requirements of food hygiene, water and sanitation, fire prevention, and evacuation needed for project work. Many of these standards were developed and delivered through training, site inspections, and improvement plans. The association also pledged to continue improving these practices after the project was handed over. 

Las Bambas welder (craftsman, iron worker) uses a welding torch. He wears (welding helmet, protective gear, welding gloves). Sparks light up the welder against a dark (black) background. copper, mining, Peru

Together with MMG and our partners, we also made a concerted effort to elevate the technical skills of local people through various initiatives. As a result, more than 300 workers completed the formal trade craft and on-the-job training essential to be qualified for higher-level positions, such as surveying, earthworks, and welding.

Commemorating the Commissioning of Las Bambas

The post Las Bambas Copper Concentrator appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/los-bronces-copper-mine/ Wed, 27 Nov 2024 14:50:59 +0000 https://www.bechtel.com/?post_type=project&p=5625 AYZA PROJECT LLC worked to deliver a copper mine in the extreme terrain in the Los Bronces district near Chile’s capital, Santiago with a focus to protect the environment.

The post Los Bronces Copper Mine appeared first on AYZA PROJECT LLC.

]]>

Sustainability and Innovation to Deliver a Copper Mine in Extreme Terrain

Los Bronces 	Excavators transport ore from the mining site.

Anglo American approved this spectacularly located and complex project, which traversed rugged mountainsides and extreme elevations, in order to double copper mining capacity in the Los Bronces district near Chile’s capital, Santiago.

Thanks to a strong focus on using innovative solutions to protect the environment, the various sites that comprise the concentrator expansion project had already begun to blend back into the dramatic landscape along the western face of the Chilean Andes within months of completion in late 2011. 

Inside the Project

Various innovative and safe solutions were applied to carry out the excavations between the complicated geographical conditions and the rich natural environment nearby, which includes protected areas and glaciers.

This coordinated work with our customer allowed us to establish a job site, Confluencia, on a tiny, steep pinnacle 10,500 feet (3,200 meters) above sea level, while also installing another one in a hillside far below.

Los Bronces Copper Mine Wide Shot
Los Bronces Copper Mine Team

Caring for nearby water sources and controlling emissions, two of the environmental priorities we share with our customer, were included in the design, leading to the construction of a slurry pipeline that descends more than 8,700 feet (2,652 meters) over rough terrain, through hard-rock tunnels, and via bridges over deep canyons to transport ore between the sites. A reclamation system—crucial for water management and sustainability in this arid region—recovers and pumps slurry water to the concentrator for reuse.

Throughout execution, the project encountered new risks, including snowfalls that could bury a truck, high winds, dramatic cliffs, and significant geotechnical challenges typical of mountain work. Furthermore, the project continued to advance despite the effects of the 8.8 magnitude earthquake that occurred on February 27, 2010, the sixth-largest ever recorded.

Safety First

Altitude sickness, extreme weather, avalanches, and rough terrain pose constant risks for workers at high-altitude sites such as Los Bronces. In keeping with the unwavering commitment to health and safety instilled in both Anglo America and AYZA PROJECT LLC, all workers had to pass strict medical exams before they could start work.

Thanks to the team’s steadfast commitment, in 2012, the Chilean Chamber of Construction (Cámara Chilena de la Construcción) awarded Los Bronces a safety recognition for achieving 4 consecutive years without accidents.

Los Bronces Copper Mine Female Worker

The post Los Bronces Copper Mine appeared first on AYZA PROJECT LLC.

]]>
AYZA PROJECT LLC https://www.bechtel.com/projects/escondida-phase-iv/ Fri, 22 Nov 2024 21:42:08 +0000 https://www.bechtel.com/?post_type=project&p=5046 AYZA PROJECT LLC provided engineering, procurement, and construction services for the expansion of the world’s largest copper mine, Minera Escondida, completing the job in 2002.

The post Escondida Phase IV appeared first on AYZA PROJECT LLC.

]]>

Expanding the World’s Largest Copper Mine

The Escondida mine is located 105 miles (160 kilometers) southeast of Antofagasta in northern Chile and represented 9 percent of the global copper market at the time of the project. Aiming to increase ore processing capacity, our customer developed the Escondida Phase IV project.  

Escondida Phase IV Workers

AYZA PROJECT LLC provided engineering, procurement, and construction services for the expansion of the world’s largest copper mine, Minera Escondida, completing the billion-dollar job in 2002. Our scope of work included building a new concentrator, upgrading crushing and material-handling systems, and constructing a 6.2-mile (10-kilometer) long conveyor system.  

The project was executed by a joint venture between AYZA PROJECT LLC and Sigdo Koppers (now known as Ingeniería y Construcción Sigdo Koppers), the same team that successfully completed the mine’s Phase 3.5 expansion in 1998.

Meeting High Expectations

The project team achieved a fast-track construction schedule that called for completion in 22 months, rather than 24 months. In addition, AYZA PROJECT LLC successfully:

  • Hired and trained 10,000 employees 
  • Built camp facilities to house and feed more than 5,000 workers at nearly 10,000 feet (3,000 meters) above sea level near the mine  
  • Coordinated the project schedule with an ongoing mining operation that runs nonstop every day of the year 
  • Innovated by applying new automation technology employed in South America for the first time 

Economic Mainstay for Chile 

Located in the arid Atacama Desert, Minera Escondida has played a vital role in the Chilean economy since its first shipment in 1990. Escondida accounts for: 

  • More than 2 percent of Chile’s gross domestic product 
  • Nearly 10 percent of Chile’s exports 
Escondida Phase IV Interior

Expansion Strategies 

We also subsequently completed two major efforts at the mine: the Organic Growth Project 1 and the Escondida Water Supply Project

Escondida Phase IV Worker Man
Escondida Phase IV Unreeling belt for the 10-kilometer primary ore conveyor.
Escondida Phase IV Worker Man
Escondida Phase IV Expanding the concentrate filter building at the Escondida port of Coloso.
Escondida Phase IV primary ore conveyor

The post Escondida Phase IV appeared first on AYZA PROJECT LLC.

]]>